Article 99.

§ 1.

The Environment Permit shall lapse ipso jure in each of the following cases:

if the licensed urban development actions are not started within two years of the final Environment Permit being granted;
if the licensed urban development actions are interrupted for more than three successive years;
if the licensed urban buildings are not windproof within five years after the final Environment Permit has been granted;
if operation of the licensed activity does not start within five years of the final Environment Permit being granted;
if the retail activities do not commence within five years after the granting of the final Environment Permit.

 

The period stated in the first paragraph, 1°, can, however, at the request of the licence holder, be extended for a period of two years if he demonstrates that the non-realisation is the result of an unusual cause that cannot be attributed to him. The permitholder must submit the application for the extension, under penalty of expiry, with a secured dispatch and at least three months before the expiry of the original expiry period of two years to the authority that issued the permit. That authority will only refuse the request for the extension if:

there is no strange cause that cannot be attributed to the permit holder.
the requested and licensed actions are in conflict with urban development regulations or parcelling regulations that have since been amended.

 

The government delivers its decision no later than the day of the expiry of the original expiry period of two years. In the absence of a decision, the extension is deemed to have been approved. If the extension is approved, the terms stated in the first paragraph, 3° and 4°, are also extended by two years.

 

If the Environment Permit expressly mentions the various phases of the construction project, the time limits of two, three or five years stated in paragraph 1 shall be calculated per phase. For the second and subsequent phases, the time limits for lapsing shall therefore be calculated from the start date of the phase in question.

 

§ 2.

The Environment Permit for the operation of a classified facility or activity shall lapse ipso jure in each of the following cases:

if the operation of the licensed activity or facility is interrupted for more than five successive years;
if the classified facility is damaged by fire or explosion caused by its operation;
if operation is completely and definitely stopped on a voluntary basis in accordance with the conditions and rules stated in the Decree of 9 March 2001 governing the voluntary, complete and definitive cessation of production of all animal manure from one or more species of animal and its implementing orders. The Government of Flanders can establish more specific rules for notification of stoppage.

 

§ 2/1

The Environment Permit for carrying out retail activities will automatically expire if the retail activities are interrupted for more than five consecutive years.

 

§ 2/2

The Environment Permit for changing the vegetation will automatically lapse if the modification of the vegetation does not start within two years after the final Environment Permit has been granted.

 

§ 3.

If the cases stated in paragraph 1 relate to part of a construction project, the Environment Permit shall only lapse for the unfinished part of a construction project. A part is only finished when it can be regarded as a separate construction that satisfies the structural requirements, where applicable after the unfinished parts have been dismantled.

 

If the cases stated in paragraph 1 or 2 only relate to part of the operation of the classified facility or activity, the Environment Permit shall only lapse for that part.