The work plan.


Article 5.2.1.3.

1.

At the commencement of operations the operator has a work plan. According to the kind of establishment concerned, this work plan comprises:

1

a well-organised and clear manual for the operation of the establishment;

2

the organisation of waste materials delivery;

3

the organisation of the processing of the delivered waste materials;

4

a plan of the storage and treatment spaces, indicating the nature and the storage capacity for the different waste materials.

5

the organisation of the removal of waste materials;

6

the processing method for the delivered waste materials if the establishment is out of service (temporarily);

7

the drainage plan including the schedule, organisation and introduction of measures for the drainage of the establishment and/or the site;

8

measures to be taken in the event of malfunctions or undesired side-effects and to prevent nuisance.

2.